Project Objectives
- Improving Product of Irrigation Water by efficient conveyance and its effective farm level use.
- Production of more profitable crops through HEIS.
- Strengthening the private sector service delivery.
- Capacity building of stakeholders in better managing irrigation water.
Sponsoring
- Punjab Agriculture Department through World Bank.
Execution
- Punjab Agriculture Department (Water Management Wing)
- District Government.
- Sypply & Services companies.
- Water Users Associations.
Monitoring
Project Duration
- 60 months (2012-13 to 2020-21)
|


Project Digest |
Rs. |
Government Share(World Bank Loan)
Farmer's Contribution |
21,249.997m
14,750.709m |
Total Cost |
36,000.705m |
|
|
|
 |
|
|
|
 |
Project Components
Sr. No |
Component |
Targets (2012-13 to 2020-21 |
Current Status |
1 |
Installation of high efficiency irrigation system |
120000 (acres) |
In Progress |
2 |
Strengthening of Laser leveling Services. |
3000 (Nos.) |
Completed |
Additional Target (PIPIP + ADP) |
6000 (Nos.) |
In Progress |
3 |
Improvement of Canal Watercourses. |
5500 (Nos.) |
In Progress |
4 |
Completion of Partially improved watercourses. |
1500 (Nos.) |
Completed |
5 |
Irrigations Schemes in Non-Canal commanded areas. |
2000 (Nos.) |
Completed |

|
Monitoring Status of PMU
The Program Monitoring Unit (PMU) with its existing setup i.e. provincial headquarter and regional offices will continue to monitor all the activities to be carried out for proposed project under the administrative control of the Secretary Agriculture. The funding for the same will be provided by the Punjab government through non-development budget (Grant No. 18) in accordance with existing arrangements.
Reference (PC-1, Page No. 63, Paragraph No. 1)
|
|
 |
|
|
|